At-Risk Core Network Backbone Maintenance

Friday, 6 March 6 hours
Scheduled
Scheduled

We have been notified of planned maintenance by our WAN backbone carriers, with activities overlapping during the dates and times listed below. As a result, network capacity and resilience for traffic to and from DCN3 will be reduced for the duration of the work.

Accordingly, we are designating this period as AT RISK.

Description of Work

Carriers will be performing maintenance on Ethernet wavelength services affecting 2 routes in and out of DCN3. The maintenance activities are not expected to last longer than 30 minutes.

Time and Date

  • Start: 00:00 06 March 2026
  • Finish: 06:00 06 March 2026

Location

DCN3

Anticipated Impact

No loss of traffic is expected. But due to reduced resiliency during the maintenance window we are classifying this as an AT RISK period.

Should you require further information, please contact us via our customer portal.

Affected components
  • Network Infrastructure
    • UK Network
      • Nottingham